Project Summary
Saulsbury provided the construction installation services for the rebuild of a client’s hot side electrostatic precipitators (ESP) at a 648-megawatt, single turbine plant in Boone County, Kentucky.
This improvement allowed Saulsbury’s client to safely close its ash basins and significantly decrease emissions.
—
Scope of the Project
- Replaced internal collecting plate system
- Replaced existing weighted wire system with new RY system
- Modified existing gas distribution devices within ESP inlet ducting
- Modified existing ash distribution devices within ESP outlet ducting
- Tie-ins to existing facilities for services
- Installed new TR sets and rapper system
- Unloaded and staged ESP internal components
- Erected and modified monorail system
- Removed existing electrical gear
- Installed new electrical gear, cable trays, and power and control wiring
- Installed penthouse module system
- Insulated new penthouse modules to attain new hot/cold roof condition
- Installed new fire protection system extension piping
- Installed new vacuum piping system extension
- Installed new gutter and downspout system for penthouse roof drainage